New Delhi, Nov. 20 -- India's first bullet train is moving closer to reality, with the initial service on the Mumbai-Ahmedabad high-speed rail corridor scheduled to begin between Surat and Vapi in the last quarter of 2027, Railway Minister Ashwini Vaishnaw has said.
In a recent article outlining the progress of the ambitious 508-km project, Vaishnaw said construction was advancing across the corridor, with major work on elevated tracks, tunnels, stations and electrification nearing completion. The corridor is designed for a maximum speed of 350 kmph, with trains expected to operate at 320 kmph, reducing travel time between Mumbai and Ahmedabad to one hour and 58 minutes.
As of September 2026, 456 km of pier work and 371 km of viaduct construction had been completed. Around six lakh noise barriers have been installed along 299 km, while 9,300 overhead electrification masts have been erected across 206 km. Civil construction at eight stations is complete, with finishing work underway.
One of the project's most challenging components is the 21-km tunnel in Maharashtra, including a seven-km stretch beneath Thane Creek. Two tunnel boring machines, each weighing over 3,000 tonnes, were launched in July 2026. The underground station at Bandra Kurla Complex will be 32 metres below ground, with three levels and six platforms.
More than 90 per cent of the corridor, covering around 465 km, is being built on elevated viaducts. The project is also using the Full Span Launching Method, which allows 40-metre-long, 970-tonne concrete girders to be installed in a single operation, making construction around 10 times faster than conventional segmented methods.
On the manufacturing front, ICF and BEML are developing the indigenous B28 trainset, designed for speeds of up to 280 kmph. Its first body frame has been completed and is undergoing structural testing, with track trials expected by mid-2027. A faster B35 trainset, designed for 350 kmph, is planned next.
The corridor is expected to provide the technological foundation for future high-speed rail projects. The Union Budget 2026-27 announced seven additional corridors covering nearly 4,000 km, with an estimated investment of Rs 16 lakh crore. Vaishnaw said the experience gained would help build domestic manufacturing capacity, common standards and technical expertise for India's high-speed rail network.