Amausi biogas plant misses another deadline, remains stalled
LUCKNOW, Nov. 27 -- Despite years of planning, repeated assurances and multiple deadline extensions, the Lucknow Municipal Corporation's (LMC) ambitious compressed biogas (CBG) plant in Amausi remains stalled, even after the infrastructure hurdle cited by officials was resolved. The project, originally scheduled for inauguration in November 2025, has yet to become operational, raising questions over the civic body's waste-to-energy strategy at a time when Lucknow has again secured the third position in the Swachh Survekshan rankings.
The absence of operational biogas infrastructure has also added to the city's challenges in managing and processing organic waste. The Amausi facility was envisaged as an important component of the LMC's waste-management strategy, as it would process cow dung and vegetable waste to generate compressed biogas instead of allowing such waste to add to the conventional disposal burden.
The LMC has now written to the executing agency, asking it to commence work after the Lucknow Development Authority (LDA) completed the approach road connecting the project site. However, the civic body is yet to announce a fresh timeline for starting construction and commissioning the plant.
Speaking to HT, LMC environmental engineer Sanjeev Pradhan, who is overseeing the project, said the delay in constructing the approach road had prevented the agency from starting work.
"The approach road has now been completed. We have issued a letter to the agency asking it to start the work," Pradhan said.
When HT questioned the repeated delays despite earlier commitments, Pradhan attributed the lack of progress primarily to the pending approach road, stating that the agency could not begin work without the required connectivity to the site.
The latest development comes after the project had already faced years of delays. In April 2025, the LMC announced that it had finally resolved the land-related hurdle for the proposed plant, clearing the way for construction after nearly two years of waiting.
The project is planned across 7.5 acres in Amausi village under Sarojini Nagar tehsil.
However, despite the land hurdle being resolved in April 2025 and the subsequent November 2025 inauguration target, the project has failed to take off.
The delay also highlights the larger implementation challenges facing the LMC's biogas infrastructure. In an HT report published in August 2026, the civic body failed to commission two compressed biogas plants despite years of planning and repeated deadline extensions.
While the two projects remained incomplete, the LMC had also moved ahead with plans for a third biogas plant near the cattle colony in Zone 6 to prevent cow dung from entering the Gomti river....