MC for speedy work at Dadumajra waste site
Chandigarh, May 6 -- The firms associated with the Dadumajra dumping ground project were on Tuesday asked to ensure expeditious bio-mining and clearance of legacy waste without delay. The directions were issued by municipal commissioner Amit Kumar who flagged a few issues during an inspection drive and sought an action-taken report within a week.
According to the municipal corporation, records pertaining to refuse-derived fuel testing and inert material were found incomplete, following which the executive engineer (solid waste management) was asked to ensure strict compliance with contractual provisions and to examine the matter for appropriate penal action against the agency. "Adopt a mission-mode approach with round-the-clock operations, enhanced machinery deployment and optimum manpower," he stated while ordering a daily monitoring of progress, regular reporting and strict adherence to scientific and environmentally compliant practices.
In addition, MC chief engineer Sanjay Arora inspected the dry waste processing plant where it was noted that weighbridge records were not being properly maintained in accordance with the approved norms.
The MC has been facing the heat due to missed deadlines. It was first slated for completion in July 2025, then September 2025 and later November that year. It is finally expected to be cleared by May 31....
इस लेख के रीप्रिंट को खरीदने या इस प्रकाशन का पूरा फ़ीड प्राप्त करने के लिए, कृपया
हमे संपर्क करें.