Atlanta, Nov. 2 -- SWAINSBORO, CITY OF has issued a solicitation notice (PE-66723-NONST-2027-000000023) titled ‘City of Swainsboro, Georgia: North Green Street Sidewalk Improvements’. Notably, the event starts on Oct. 30 and ends on Dec. 3.

Further, the description states, “The project will consist of approximately 1, 153 LF of concrete curb and gutter; 549 SY of 5-foot-wide, 4-inch-thick concrete sidewalk; 86 SY of 4-foot-wide, 6-inch-thick concrete sidewalk; 94 SY of 6-inch-thick concrete valley gutter; and 2 EA of concrete flume, traffic control, grassing of disturbed areas, and all related appurtenances.

Time allotted for completion shall be 90 consecutive calendar days for substantial completion and 120 consecutive calendar days for ...