Dhaka, Nov. 23 -- The Rooppur Nuclear Power Plant in Ishwardi upazila of Pabna district, has started supplying electricity to the national grid for the second time on a trial basis on Monday.

Dr Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant construction project, said around 300-350 megawatts of electricity would be supplied to the national grid on a trial basis for 10 to 24 hours during this second phase.

Various technical tests will be conducted during this period to assess the plant's power generation system and its integrated operation with the national grid, he said.

Earlier, the plant began its first trial supply to the national grid on November 17.

During the initial phase, the first unit generated up to ...