Cash issues clog Suchitra-Kompally Flyover completion, shows RTI
Hyderabad, June 8 -- The long-pending Suchitra-Kompally Flyover project on National Highway (NH)-44, one of the upcoming flyovers in Hyderabad, has been consistently delayed primarily due to cash flow issues faced by the contractor, according to information disclosed by the National Highways Authority of India (NHAI) under the Right to Information (RTI) Act.
The 10-kilometre-long stretch between Gundlapochampally and Bowenpally is being built to ease congestion on one of Hyderabad's busiest highway corridors connecting the city with Medchal and northern Telangana.
The RTI, filed by Manda Vishnu Vardhan, a law student, sought data on the flyover construction and road expansion works between Secunderabad and Medchal.
The project was sanc...