Construction of Tulsipur-Ghorahi road resumes after seven-year delay
Nepal, Nov. 23 -- Construction of the four-lane road connecting two major cities in Dang, Ghorahi and Tulsipur, has resumed after years of delays, but progress remains slow, with only 17 percent of the work completed in the past 15 months.
The 21.58-kilometre road has been a major source of inconvenience for residents, remaining dusty during dry weather and muddy during the monsoon. Frequent accidents on the dug-up road have also claimed several lives.
Construction of the Ghorahi-Tulsipur road began in 2019 with a loan from India's Export-Import Bank. India's Tathya Engineering and Infra Project was initially awarded the contract but failed to complete the work, leaving the project stalled. The government terminated the contract in 202...