RWE to build 400 MW battery to ease grid congestion in Noord-Brabant
Netherlands, Sept. 21 -- The Moerdijk power station site will be home to a flagship large-scale battery system in the Netherlands. RWE has taken the final investment decision to build a 400 megawatts (MW) and 1100 megawatt-hours (MWh) battery storage system at the site. It will consist of 208 containers with lithium-ion batteries and can deliver its full output for almost three hours. Construction is scheduled to start in due course, commissioning is planned for second quarter of 2028. Moerdijk battery to relieve grid congestionThe new battery system will make best use of the existing infrastructure: It will be connected to the national grid via the existing substation at the RWE power plant in Moerdijk. Through capacity steering agreements...