Raft foundation first concrete pour completed for Address Residences Zabeel
China, Feb. 9 -- CSCEC has recently completed the first concrete pour of the large-volume raft foundation for Building Two of the Address Residences Zabeel residential project, following 36 consecutive hours of coordinated operations.The pour involved the one-time casting of a raft foundation with a thickness of 3.5 meters and connecting beams with a maximum elevation difference of 5.2 meters, bringing the total local structural height to 8.7 meters. A total of 7,458 cubic meters of concrete was placed. Five truck-mounted concrete pumps were deployed simultaneously, with precise process control implemented throughout to achieve a single, continuous pour.During construction, the project team strictly complied with local construction standard...