United States, Oct. 13 -- Oracle announced a proposed Energy Service Agreement with El Paso Electric (EPE) for Project Jupiter to support late-stage construction, initial commissioning, emergency backup power at the site and to meet life safety needs for New Mexican workers at the data center.As indicated earlier this year, the primary power source for Project Jupiter will continue to be provided by the Bloom Energy fuel cell microgrid. There is no change to our plan.As part of the Energy Service Agreement, Oracle expects to pay $10 million for power annually for 10 years even if its usage is below contracted levels. This agreement helps offset shared electric system costs that would otherwise be borne by EPE's New Mexico customers and supp...