India, Oct. 2 -- Adani Green Energy Ltd (AGEL), India's largest renewable energy company, has expanded its operational Battery Energy Storage System (BESS) capacity to 6.63 gigawatt-hours(GWh) at Khavda, Gujarat, from 3.55 GWh in June 2026. AGEL nowaccounts formore than 50% of India's operational BESS capacity of about12.6 GWh. This milestone consolidatesKhavda's position as the world's largest operational battery energy storage installation at a single location, with 6.63 GWh of operational capacity. AGEL achieved the 6.63 GWh milestone within 14 months of commencing on-site BESS construction at Khavda, Gujarat with this latest capacity addition being commissioned in just 10 months from the start of its construction. The BESS is integrat...