Cabinet approves Green Energy Corridor Phase-III scheme for Development of Intra-State Transmission System with Battery Energy Storage Systems
New Delhi, Oct. 1 -- The scheme also provides for deployment of 50 GWh of Battery Energy Storage Systems (BESS) at the Renewable Energy (RE) developer/generator end or any other location of importance for grid flexibility to address intermittency, congestion, peak-hour curtailment and meet non-solar hour demand. The scheme will facilitate grid integration and power evacuation with in the States/UTs of India.
The scheme is targeted to be set up by FY 2032-33 with total project outlay of Rs.1,86,405 crore, comprising Rs.1,36,378 crore for the development of Intra-State Transmission Systems (InSTS) under GEC-III, Rs.50,000 crore for 50 GWh of Battery Energy Storage Systems (BESS). The Scheme involves a total Central Financial Support of Rs....