DENGKIL, April 1 -- The redevelopment project for dilapidated buildings at Sekolah Jenis Kebangsaan Tamil (SJKT) Dengkil here is progressing smoothly and is ahead of schedule, with completion expected earlier than originally planned, said Deputy Education Minister Wong Kah Woh.
Wong said the project's physical progress has reached 65.14 per cent compared to the original target of about 50 per cent in March, placing it 15.14 per cent ahead of schedule and approximately 70 days ahead of the contract timeline.
"With this excellent contract performance, we hope to bring forward the project completion date from the original target of Oct 12 this year.
"Based on current progress, we are working to accelerate it further to about 90 days ahead...
Click here to read full article from source