India, March 11 -- The Government of India has issued a release:

Period

Outlay

2009-14

Rs.1,171 crore/year

2025-26

Rs.23,778 crore (More than 20 times)

SN

Location

Details

1

Bandra Terminus

3 Pit Lines have been completed

2

Mumbai Central

Platform extension for 24 LHB coaches

3

Jogeshwari

2 additional platforms

4

Dadar

1 additional platform

5

Vasai road

6 platforms, 3 pit lines and 5 stabling lines

6

Panvel-Kalamboli

5 platforms , 4 pit lines and 2 sick lines

7

Kalyan

6 platforms and 4 pit lines

8

LTT

4 platforms and 2 pit lines

9

Parel

6 platforms, 5 pit lines, 6 stabling lines

10

Virar

25 stabling lines

11

Dahanu road

11 stabling lines

12

Mira road

25 stabling lines

SN

Name of Project

Cost ...