India, March 16 -- The Government of India has issued a release:

Financial Year

Energy Requirement

Energy Supplied

Energy not Supplied

Peak Demand

Peak Met

Demand not Met

(MU)

(MU)

(MU)

(%)

(MW)

(MW)

(MW)

(%)

2022-23

15,13,497

15,05,914

7,583

0.5

2,15,888

2,07,231

8,657

4.0

2023-24

16,26,132

16,22,020

4,112

0.3

2,43,271

2,39,931

3,340

1.4

2024-25

16,93,959

16,92,369

1,590

0.1

2,49,856

2,49,854

2

0.0

2025-26 (upto February, 2026)

15,59,936

15,59,482

454

0.0

2,45,444

2,45,416

28

0.0

As on 31.01.2026, the total 'installed power generation capacity' in the country is 5,20,511 MW.

There is adequate availability of power in the country. Present installed generation capacity of the country is 52...