JABALPUR, India, March 31 -- Madhya Pradesh High Court issued the following judgment/order on Feb. 27:
1. Petitioner is aggrieved by an office order dated 23.01.2026, whereby the petitioner has been declared as a non performer. Petitioner is also aggrieved by an order dated 17.02.2026, whereby a decision has been taken by the respondents to carry out balance work at the risk and cost of the petitioner. Petitioner is also aggrieved by the order dated 20th February, 2026, whereby the petitioner has been debarred for a period of one year from participating in the National Highway Projects and other Centrally Sponsored Road Projects.
2. Learned counsel for the petitioner submits that insofar as the declaration of petitioner as a non performe...