RANCHI, India, March 28 -- Jharkhand High Court issued the following order on Feb. 25:

1. Heard learned counsel for the parties.

2. The petitioner, claiming to be the L1 bidder in the tender process, instituted this petition for acceptance of its bid. This petition was instituted on 09.05.2025. All defects were ultimately cleared on 13.02.2026, after opportunities were granted to the petitioner to clear the same.

3. Mr. Piyush Chitresh, learned AC to AG now states that since there was no interim relief, a very short-term tender notices dated 06.01.2026 and 10.01.2026 were issued for the same work (second call), pursuant to which work orders have been issued on 27.01.2026 and 17.02.2026.

4. Neither the said tender notices nor the fres...