India, Feb. 14 -- The Government of India has issued a release:

Feature

Details

Project Name

Widening of National Highway-167 from Gudebellur to Mahabubnagar on the Hyderabad-Panaji Economic Corridor to 4-Lane Standard in the State of Telangana with a Total Project Length of 80.01 km and Total Capital Cost of Rs.3175.08 crore on Hybrid Annuity Mode (HAM) under NH (O) scheme

Corridor

Gudebellur - Mahabubnagar section of Hyderabad - Panaji Economic Corridor

Length (km)

80.01 (including bypass & realignments over 36.8 km)

Total Civil Cost including Utility Shifting (Rs Cr.)

1868.90

Cost of Pre-construction Activities (LA Cost + Other Cost)

459.11

Total Capital Cost (Rs Cr.)

3175.08

Mode

Hybrid Annuity Mode (HAM)

Major Roads Co...