HC directs SJVNL to pay interest to Luhri Hydro project landowners
Shimla, Oct. 16 -- The Himachal Pradesh high court has directed SJVN Limited (SJVNL) to pay solatium, interest and other statutory benefits to landowners whose land was acquired for the 210 MW Luhri Hydro Electric Project (Stage-I), holding that the company is bound by the conditions imposed by the state government while approving negotiated land compensation rates.
Justice Sandeep Sharma, while allowing a bunch of petitions, directed SJVNL to disburse the benefits payable under Sections 30(1), 30(3) and 80 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, within three months.
The dispute arose from the procurement of private land in villages, including Badrash and Nirath, for the hydroelectric project. Instead of proceeding through formal compulsory land acquisition, the company obtained the land through negotiated rates finalised by a government-constituted negotiation committee.
The Himachal Pradesh government, while approving the negotiated rates on March 6, 2020, had specifically stipulated that SJVNL would comply with the mandatory provisions of the 2013 Land Acquisition Act relating to compensation, rehabilitation and resettlement.htc...
इस लेख के रीप्रिंट को खरीदने या इस प्रकाशन का पूरा फ़ीड प्राप्त करने के लिए, कृपया
हमे संपर्क करें.