GMDA to expedite approvals for Gurugram metro corridor
Gurugram, Nov. 27 -- The Gurugram Metropolitan Development Authority (GMDA) will expedite design approvals, utility shifting and removal of structures obstructing construction along the Gurugram metro corridor, officials said on Thursday.
The directions were issued by GMDA chief executive officer Dushmant Kumar Behera during a coordination meeting with Gurugram Metro Rail Limited (GMRL) officials on Wednesday.
"The plans for the flyover and underpass at Bakhtawar Chowk and the proposed design of the reversal track near Millennium City Centre must be processed immediately," a senior GMDA official said.
GMRL officials said the design of the proposed double-decker flyover at Bakhtawar Chowk was submitted to GMDA on August 27 and a revised plan on November 2, but approval is still awaited.
The GMDA is yet to share plans for pillar placement at Z Chowk, near Millennium City Centre station, delaying construction of the reversal track.
Foot overbridges in sectors 37 and 9 are yet to be removed, holding up construction between Umang Bhardwaj Chowk and Sector 9. The traffic diversion plan for the 1km stretch between Dada Bhaiya Chowk and ESI Hospital in Sector 9 also awaits approval.
A proposed land exchange involving a 0.9-hectare forest department plot earmarked for a metro station at the Sector 10 e-bus depot remains pending.
"Metro work has gained pace and we now need carriageways free of obstacles. We hope utility shifting and other works will now be expedited," a senior GMRL official said.
GMRL is executing the first phase of the metro, connecting Millennium City Centre metro station to Sector 9. It has floated a tender for the second phase, from Sector 9 to Cyber City, at an estimated cost of Rs.1,662 crore....