Gurugram, Nov. 28 -- The National Highways Authority of India (NHAI) on Friday said the Bilaspur flyover on the Delhi-Jaipur highway will be fully opened to traffic by December 20. Bituminous surfacing has begun on the Jaipur-bound carriageway, which is expected to open in the first week of December, said officials. Meanwhile, NHAI plans to open the Rewari-bound carriageway of the Pahari railway overbridge on the Gurugram-Pataudi highway by December 31. "The other carriageway will be completed by March 2027," a senior NHAI official said. Around 95% of the 45km Gurugram-Pataudi-Rewari highway project, being executed at a cost of Rs.1,900 crore, is complete. The entire project is expected to be completed by March 2027, officials said. NHAI has also secured permission from the Bhakra Beas Management Board to shift high-tension power lines at Wazirpur, facilitating the opening of the flyover there. A 16-lane toll plaza at Janaula village is expected to be completed by December-end....