Parallel discom permit: Tribunal declines interim relief to pvt firm
Chandigarh, Nov. 19 -- The Appellate Tribunal for Electricity on Wednesday declined to grant interim relief to Eleven Power Private Limited, thereby declining to stay an October 28 order of the Haryana Electricity Regulatory Commission. Under that order, the regulator decided not to take further steps to give effect to a 25-year parallel power distribution license granted to the 2025 incorporated firm for Gurugram and Nuh.
The matter will now be taken up on December 2 when the government, the state-owned power utilities and HERC file their responses. P4...