New Delhi, April 24 -- The Irrigation and Flood Control Department has completed over 57% of desilting work across major drains in the Capital ahead of the monsoon season, officials said.

According to official data, desilting at 76 drains has reached 57.68%, with over 1.65 million cubic metres of silt removed against a target of 2.86 million cubic metres. Work on 21 priority drains has crossed 76% completion, showing significant progress in flood-prone areas.

Delhi minister Parvesh Verma said the emphasis is on timely execution. "Our priority is to ensure that all critical drains are cleared and functional before monsoon. Work is being monitored closely at every level. We have strengthened both manpower and machinery," he said.

The Naj...