NHAI to repair Hero Honda Chowk stretch, puts onus of utility shifting on GMDA
Gurugram, Oct. 29 -- The National Highways Authority of India (NHAI) will soon begin repairs on the 2.25-km stretch between Hero Honda Chowk and Umang Bhardwaj Chowk, even as the responsibility for shifting utilities for the proposed elevated road project remains unresolved.
NHAI officials said major water, sewer and stormwater pipelines along the stretch would have to be shifted before construction of the elevated road could begin.
"We had floated two tenders for overlaying and repairing the road, but no bidders came forward. We have now decided to carry out the work internally through our existing contractor. NHAI will not shift the utilities as the elevated road project is not being executed by us," said a senior NHAI official.
NHAI...
Click here to read full article from source