India, Nov. 17 -- The Maharashtra forest department has ordered an immediate halt to all work on Adani Green Energy Limited's (AGEL) 1,500 MW Tarali Pumped Storage Project (PSP) in Patan taluka of Satara district, citing the absence of mandatory prior approval from the National Board for Wildlife (NBWL).
The department also issued a show-cause notice to the company, seeking an explanation within three days on why work commenced without NBWL approval.
The company, however, has maintained that all clearances and permissions were obtained before beginning construction. It said its wildlife clearance proposal for the project had been submitted to the NBWL and was under consideration.
The November 13 notice, obtained and reviewed by HT on M...