Land hurdles leave Dwarka Expressway service roads incomplete
Gurugram, Nov. 20 -- Nearly 1.5km of service roads along the Dwarka Expressway remains incomplete despite the construction of around 25km between Bijwasan toll plaza and Elan Mall, leaving several stretches unusable for commuters, Gurugram Metropolitan Development Authority (GMDA) officials said.
According to officials, around 971 metres of service roads at four locations are yet to be constructed due to land acquisition hurdles, while another 582-metre stretch near the Pataudi Road crossing remains pending because of a proposed cloverleaf interchange.
Officials said most of the construction work was completed this year, but the non-availability of land at certain locations has prevented the authority from completing the remaining secti...