Hindon approach road from Greater Noida side to be ready by December
India, June 1 -- The six-lane 290-metre bridge across Hindon river meant to boost connectivity between Greater Noida and Noida is almost ready, but the approach road from Greater Noida side is yet to be constructed, said officials on Sunday.
While the Noida authority is set to ready its approach road in a month, the Greater Noida authority is likely to take about six monthsto ready its approach road, they added.
"The main bridge is almost complete, with only finishing work remaining. We will develop the approach road connecting the LG roundabout to Knowledge Park-III and then to the Hindon bridge. The issue is that a 100-metre stretch of land is yet to be acquired. The landowner resides in Delhi. The Authority is expediting the acquisit...
Click here to read full article from source