HC stays execution of arbitral award ordering MMRDA to pay rRs.r238.66 cr to Lodha Developers
India, Nov. 25 -- The Bombay High Court has granted a conditional stay on the execution of an arbitral award ordering the Mumbai Metropolitan Region Development Authority (MMRDA) to pay Rs.238.66 crore to Lodha Developers Ltd towards compensating losses caused by the reduction in permissible built-up area in its Wadala project.
A single judge bench of Justice NJ Jamadar rejected the MMRDA's plea for unconditional stay on the execution of the award. Instead, the court granted a stay on the condition that the MMRDA deposits Rs.145.44 crore with the court within six weeks. The interim order was passed on a commercial petition filed by the MMRDA, challenging the arbitral award dated October 17, 2025, passed by a sole arbitrator.
The dispute...