GMRL floats tender to start pre-construction activities for Phase-2 metro corridor
Gurugram, Oct. 13 -- To prevent delays in the construction of Gurugram Metro's Phase 2 corridor, Gurugram Metro Rail Limited (GMRL) has decided to undertake utility shifting and other preparatory work in advance, floating a single tender for relocating power lines, water and sewer pipelines, removing trees and widening roads along the 14.2km stretch from Sector 9 to Cyber City.
GMRL, which is executing the project, on Monday floated a Rs.62 crore tender to hire a contractor to verify an earlier survey of utilities, identify those that need to be relocated and carry out the shifting work. The contractor will also be responsible for preparing and implementing a traffic management plan to divert vehicles during the work.
A senior GMRL offi...
Click here to read full article from source
To read the full article or to get the complete feed from this publication, please
Contact Us.