India, April 8 -- Power supply to Yashwin Housing Society in Hinjewadi was restored on Tuesday (April 7) morning after being disrupted for nearly 22 hours due to a fault in a high-voltage line during metro construction work. Maharashtra State Electricity Distribution Company Limited (MSEDCL) officials resumed supply at 10.50 am following continuous repair efforts.
The outage began at 12.48 pm on Monday (April 6) when a 22 kV high-voltage line supplying electricity to the society developed a fault near a metro station construction site close to a private company in Hinjewadi Phase 3. The line feeds three transformers catering to around 572 consumers.
MSEDCL officials said layers of concrete had been poured over the underground cable duri...