Chandigarh: rRs.r81cr parking project awaits opening for two months at Sector 43 district courts complex
Chandigarh, June 12 -- The demand for parking at the judicial complexes is still in the queue as the Rs.81-crore multi-level parking project at the district courts complex in Sector 43 faces a delay in operationalisation, despite construction wrapping up two months ago.
The project began in July 2022 and the facility was developed by the engineering department of the UT administration to address the growing demand for parking at the judicial complexes. The structure has a capacity of 1,278 equivalent car units (ECU) and comprises a basement, ground floor, first floor, second floor and terrace level.
The project was allotted to Hansraj Kohli & Company in September 2022 with a two-year completion target. However, the project missed its de...