India, June 4 -- The Noida Power Company Limited (NPCL) has commissioned a new 12.5 MVA, 33/11 kiloVolt (kV) substation in Site-4 area, and is set to operationalise another substation in Ecotech-3 later this week to boost power infrastructure across Greater Noida amid a record electricity demand in this ongoing summer.

Greater Noida's peak power demand touched a record 866 MW on May 28 this year, surpassing the previous all-time high of 832 MW recorded on June 12, 2025.

The new substation, which operational this Monday, is expected to improve power supply reliability and network flexibility in Site-4, Swarn Nagri and Sector-36 areas. The additional capacity will help reduce the load on the existing Sector-36 substation, said NPCL offici...