Goa, Nov. 27 -- Rail Vikas Nigam Limited (RVNL), a public sector undertaking under the Ministry of Railways, has achieved a major construction milestone on Uttarakhand's Rishikesh-Karnaprayag rail project with the breakthrough of Tunnel-14, measuring approximately 6.59 km, in Rudraprayag district. The work required navigating difficult Himalayan terrain marked by loose soil beneath populated settlements, unstable slopes, and strict requirements for controlled blasting to limit vibration and risk to nearby structures.
A particularly demanding segment involved excavating a 110-metre stretch of the triple-track tunnel through loose ground at Portal-1 (T14P1), where overburden depth measured only 20 to 30 metres. Because the alignment runs b...