Dehradun, April 17 -- Garhwal Post Bureau
Kiccha, 16 Apr: Chief Secretary Anand Bardhan conducted a site inspection of the 280-bed satellite AIIMS under construction in Kichha on Thursday, which will cost Rs 351 crore. During the inspection, he directed the CPWD Engineer to expedite work by increasing the number of workers and equipment, and to complete the hospital by July. He urged that the hospital buildings be prioritised by a work plan so that OPDs can begin in August. CPWD
Engineer Utpal Tripathi stated that the hospital will be completed by 30 July. He added that more than 85 percent of the residential buildings are complete and will be completed by May. The hospital's roads will also be completed by May, and plantations will beg...
Click here to read full article from source