Mumbai, Nov. 16 -- India has approved plans for a high-capacity power transmission corridor to transport electricity from renewable generation hubs in the west to industrial and urban demand centres in the east. The project is estimated to cost nearly Rs. 688 bn and is expected to take about six years to complete.

The planned 1,150 kV system will be India's highest-voltage power network. It is designed to carry substantially larger volumes of electricity than the existing 765 kV lines, enabling the national grid to move power more efficiently across long distances.

The approval was granted by India's national transmission panel, according to minutes of a meeting released on Tuesday. The project comes as the country rapidly expands renewable energy and battery storage capacity while pursuing a target of 500 GW of non-fossil power generation by 2030, compared with more than 300 GW currently.

Existing 765 kV lines would require additional transmission corridors and land to carry rising electricity volumes. A 1,150 kV network can move more power along fewer lines and across a smaller land footprint, while also reducing transmission losses.

The network is being planned as renewable capacity expands in western states such as Rajasthan and electricity demand increases in eastern industrial hubs including Odisha. The first phase will connect Chhattisgarh, Odisha and West Bengal with a 6,000 MW high-voltage transmission system carrying renewable power from Rajasthan's Bhadla solar region. The corridor is intended to strengthen the grid's ability to transfer clean electricity between regions and support the country's broader energy transition.

Published by HT Digital Content Services with permission from Construction World.