Mumbai, May 6 -- The company further said that this project ranks among the largest single BESS orders awarded in India.
The scope of work included supply, civil works, and erection of 250 MW/1,000 MWh battery energy storage system (BESS) comprising 5 MWh DC containers with battery management system (BMS) and thermal management system (TMS), 33 kV panel boards, 220 kV DC & AC cables, 220 kV switchyard and all associated accessories.
The project will be executed over an 18-months period followed by a 15 years of operation and maintenance.
The project will seamlessly integrate large-scale battery storage with existing thermal power infrastructure enabling peak load management, grid stability, and efficient integration of renewable power....