Mumbai, April 17 -- The project involves construction of key bridges under the third and fourth railway line expansion between Nergundi-Barang and Khurda Road-Vizianagaram on the Bhadrak-Vizianagaram section. The total contract value stands at approximately Rs 968 crore.
The order, awarded on EPC mode, is to be executed over a period of three years and includes construction of multiple open web steel girder bridges over major rivers such as Mahanadi, Birupa, Kathjori and Kuakhai.
Earlier this month, RVNL secured an order worth Rs 242 crore from South Central Railway. The project involves upgradation of overhead electrification systems from 1x25kV to 2x25kV in the Ongole-Gudur section and is scheduled for completion within 24 months.
RV...
Click here to read full article from source
To read the full article or to get the complete feed from this publication, please
Contact Us.