Mumbai, April 23 -- In an exchange filing, the company said the order has been awarded by SJVN Lower Arun Power Development Company, a subsidiary of SJVN, for Package 2 of the 669 MW project located in the Sankhuwasabha district.

The project, to be executed over 54 months, involves critical civil and hydro-mechanical works, including the construction of tunnels, surge shafts, pressure shafts, powerhouse infrastructure, and associated systems.

The scope covers key components such as head race tunnels, access adits, pressure shafts, butterfly valve chambers, along with the installation of steel liners and other supporting infrastructure required for efficient water conveyance and power generation.

Commenting on the development, managing ...