Board of Bhansali Engineering Polymers consider expansion project progress
Mumbai, Oct. 19 -- The board of Bhansali Engineering Polymers at its meeting held on 19 October 2026 has considered the progress of the expansion project:
Expansion plan to enhance ABS production capacity from existing 75000 TPA to 100000 TPA with estimated cost of Rs.200 crores was expected to be completed by September, 2026. However, due to disturbances caused by global war scenario (i.e. Gulf War & Russia- Ukraine war) following issues are being faced:
- Delivery of imported equipment is delayed due to shortage / non-availability of shipping containers;
- Service engineers of Foreign Suppliers are unable to commit exact visit
schedules for equipment commissioning trials;
- Delivery of reactor is delayed due to distu rbed supply ch...