Rooppur power enters national grid for first time
Dhaka, Nov. 17 -- Electricity from the Rooppur Nuclear Power Plant has fed into the national grid for the first time, setting a major milestone for Bangladesh's first atomic energy facility.
Power Grid Bangladesh PLC said the trial run began after the plant in Pabna's Ishurdi Upazila synchronised with the national grid at 3:16pm on Tuesday, with output hitting 350MW by 3:45pm.
Grid synchronisation links a power station's generators to the national network, allowing engineers to match voltage and frequency before commercial generation begins.
Officials noted that test runs and safety checks will continue across different capacity levels over the coming months.
The plant's first unit achieved its first controlled nuclear reaction, or "f...