Mumbai-Ahmedabad Bullet Train Project: Second TBM Cutterhead installed at Ghansoli shaft
Mumbai, May 23 -- In a major milestone for the Mumbai-Ahmedabad High-Speed Rail Corridor, the cutterhead of the second Tunnel Boring Machine (TBM) was lowered at Sawli (Ghansoli) near Mumbai on Saturday, marking the completion of the primary assembly phase of the machine's main shield.
The massive cutterhead, measuring 13.6 metres in diameter and weighing around 350 tonnes, this component marks the final step in the primary assembly of the TBM's main shield.
The second TBM will begin its journey from Sawli (Ghansoli) near Mumbai and move towards Vikhroli.
Earlier this week, the cutterhead for the first TBM was also lowered at Vikhroli. Both machines will now undergo final assembly and commissioning trials before beginning their initial...
Click here to read full article from source