New Delhi, Oct. 5 -- The Delhi Traffic Police on Monday identified a structural bottleneck at the Old Barapullah Flyover as the primary cause behind the heavy traffic congestion witnessed following the opening of Barapullah Phase-III.

Delhi Traffic Police, in a post on X, outlined the disruption created by converging roadways.

"Main cause of traffic jam after opening of Barapullah Phase-III is structural bottleneck at Old Barapullah Flyover," Delhi Police stated.

According to the department's width analysis, traffic originating from approximately eight to nine lanes is merged into three lanes at a single bottleneck point on the older stretch of the flyover.

The Delhi Traffic Police said, "Width Analysis: - Width of Old Barapullah Flyo...