Khanh Hoa, June 1 -- The south-central province of Khanh Hoa has posted brisk compensation and site-clearance disbursements for the Ninh Thuan 1 and Ninh Thuan 2 nuclear power plant projects, clearing the way for follow-on work and keeping construction timelines on track. At a meeting on June 1, the People's Committee of Phuoc Dinh commune, host to the Ninh Thuan 1 plant, reported that compensation plans had been prepared for 852 of the 1,129 affected households and individuals, or more than 75% of the total. Another 278 cases were submitted for appraisal, an increase of 56 from the previous week. The communal administration approved compensation for 191 cases and completed payments to 51 beneficiaries, with payouts nearing 164 billion VN...