India, Nov. 11 -- 11-November -2026
Reuters reported on 11 November that India's national transmission panel approved plans for a 1,150 kV west-to-east power corridor, estimated at roughly Rs.68,800 crore and about six years to complete. The first phase would link Chhattisgarh, Odisha and West Bengal and connect with a system carrying renewable power from Rajasthan's Bhadla region. The panel's approval is a planning milestone. The cost and completion period are estimates.
The Power Times asks: Which agency owns the schedule from generation connection to delivery in the eastern grid? Can equipment makers qualify the new voltage-class components in time? Will land access, testing capacity and receiving substations be ready together, or will...