India, Nov. 17 -- India has approved plans for a high-capacity corridor to move clean power from western generation hubs toward eastern demand centres, Reuters reported on 11 November. The first phase is expected to link Chhattisgarh, Odisha and West Bengal to a system carrying power from Rajasthan's Bhadla solar region. The Ministry of Power's longer-term transmission plan already anticipates rising demand from electric mobility, data centres and industry. The decision makes a basic scheduling question more urgent. Will the line, substations and generating projects be ready at the same time?
A solar park can be built to its own schedule while an associated line is delayed by route permissions or a substation upgrade. The developer may the...