, Jan. 15 -- Construction work is actively underway at all four power units and auxiliary facilities of the Akkuyu Nuclear Power Plant (NPP) in Turkey. While commissioning activities are progressing at Unit 1, construction and installation work continue simultaneously at the other units.
A major milestone has recently been achieved at Unit 2 with the successful installation of the turbine generator stator in the turbine hall. This is one of the most important and technically challenging installation operations for the turbine equipment.
The turbine generator stator is one of the heaviest components of the power plant. It weighs 437 tonnes, measures 12 meters in length, and has a diameter of 4.2 meters. The stator was carefully placed in...