Hyderabad, Nov. 17 -- Yadadri Thermal Power Station (YTPS) is expected to become fully operational by December, with its fifth 800 MW (megawatt) unit set to start, a release from Telangana Power Generation Corporation Limited (TGGENCO) said on Tuesday, November 17.

Four are already generating electricity and supplying it to the state. The fifth unit is expected to further strengthen the supply.

According to TGGENCO, the boiler, turbine, generator, ash-handling and water-supply systems are functioning well.

Coal supply

As part of efforts to strengthen the coal-handling system and restore it to the prescribed capacity, TGGENCO has planned a phased maintenance and restoration programme.

The first coal-feeding line will be shut down from...