Court case threatens to delay Ilam fast-track, residents demand fresh contract
Nepal, Nov. 23 -- Residents of Ilam have urged the government to fast-track a new construction contract for the Belase-Golakharka section of the Mechi Corridor after the former contractor challenged the termination decision in court, raising fears of another prolonged delay.
The contractor failed to complete even half of the 9.5 kilometre road section within five years, despite receiving a two-year deadline and multiple extensions. The Road Division Office published the contract termination notice on October 29. The company subsequently approached the Patan High Court, seeking an interim order against the decision.
The legal dispute has alarmed residents, who fear a repeat of the four-year delay that affected the Damak-Chisapani road p...