Spain, June 30 -- Plenitude announces the start of production at its Villarino photovoltaic plant, located in the municipality of Villarino de los Aires, in Salamanca (Castilla y León, Spain), with an installed capacity of 220 MW. The inauguration took place in the presence of Plenitude's CEO, Stefano Goberti.The project consists of a single solar park covering approximately 286 hectares and includes more than 365,000 bifacial modules. The plant is expected to reach an estimated annual production of over 400 GWh.Construction began in October 2024 and was completed on schedule despite the challenging geotechnical and environmental conditions encountered on site, whilst ensuring compliance with the company's highest safety and quality standar...