Board of CG Power approves additional investment for capacity expansion
India, Oct. 23 -- The board of CG Power & Industrial Solutions at its meeting held on 23 October 2026 has approved the following capital expenditure projects to meet growing demand:S1 Unit (OIP), Ambad: The proposed project involves an investment of approximately Rs 300 crore to enhance the manufacturing capacity of OIP bushings and instrument transformers up to 800 kV, by 4236 equivalent units per year. The project will involve augmentation of manufacturing, assembly, testing and associated infrastructure, with production tentatively expected to commence within 30-36 months.S3 Unit-II Phase 2: The board has approved the further investment of approximately Rs 15.31 crore to enhance EHV circuit breaker manufacturing capacity by 3600 units (a...